Pump jack scaffold system used to scale the building side for the purpose of painting, siding, window installation, etc. The system is 2-man rated - 500# (people and material). Using alum-a-joint, poles can be stacked to a maximum 50' shoulder working height. Alum-a-jacks and Alum-a-benches hold the Alum-A-Scaffs while Alum-A-Braces secure the pol to the structure. The system's fall protection is the 22' Saf-T-Net and end rail system. The net and end rail fit exclusively on the Alum-A-Scaff.
Phase of Construction |
Siding, window installation |
Manufacturer’s Device Page |
Alum-A-Pole Corporation |
Installation |
Must be installed by competent person following detailed installation procedures. Warning: Users must strictly adhere to the manufacturer’s inspection, installation, maintenance and use directions; and must follow local, state and federal safety regulations. Failure to do so could result in serious injury or death. |
Manual |
Instruction Manual |
Vendor |
Lynn Ladder & Scaffolding, Associated Scaffolding, Industrial Ladder |
Cost |
Varies depending on configuration |